Our client was converting the industrial area to a new use. Having stripped out old plant, the decision was made to refurbish the damaged and soiled floor prior to the installation of racking.
The entire floor was prepared using vacuum contained diamond grinding. Weak areas of coating were removed using diamond grinders fitted with PCD segments.
There were numerous repairs which were excavated and repaired with our industrial strength resin repair material.
The floor was coated with our Britdura 750 Industrial Solvent Free Epoxy Floor Coating to our client’s layout in the colour Slate Grey with Traffic Blue for the walkway. Walking Person signs were applied.
The installation had a duration of five days commencing on a Wednesday and completing on a Sunday leaving he floor ready for scissor lifts the next day.
We retain a small in-house team of full-time employees tom install our floors.
Our client was converting the industrial area to a new use. Having stripped out old plant, the decision was made to refurbish the damaged and soiled floor prior to the installation of racking.
Facts & Figures
- Title: Industrial Flooring Refurbishment
- Completion date: August 2018
- Location: Derby
- Area: 1200 sq m
- Programme: 5 days
Requirement
Our client was converting the industrial area to a new use. Having stripped out old plant, the decision was made to refurbish the damaged and soiled floor prior to the installation of racking.
Preparation
The entire floor was prepared using vacuum contained diamond grinding. Weak areas of coating were removed using diamond grinders fitted with PCD segments.
There were numerous repairs which were excavated and repaired with our industrial strength resin repair material.
Floor Type
The floor was coated with our Britdura 750 Industrial Solvent Free Epoxy Floor Coating to our client’s layout in the colour Slate Grey with Traffic Blue for the walkway.
Signs
Walking Person signs were applied.
Programme
The installation had a duration of five days commencing on a Wednesday and completing on a Sunday leaving he floor ready for scissor lifts the next day.
Training